Major Project Milestones
MILESTONE
DATE
PWPA Effective Date
18th
January 2005
Closing Date
25th
April 2005
Payment Date/Financial Close
6
th July 2005
LNTP Refurbishment Works
18th April 2005
LNTP New B Extension
15th July 2005
FNTP Refurbishment Works
6th
July 2005
FNTP New B Extension
30
th September 2005
Group 1 COD (+450MW + 30MIGD)
1st
May 2008
Project COD (2000MW 160 MIGD)
20th July 2008