Major Project Milestones

MILESTONE DATE
PWPA Effective Date 18th January 2005
Closing Date 25th April 2005
Payment Date/Financial Close 6th July 2005
LNTP Refurbishment Works 18th April 2005
LNTP New B Extension 15th July 2005
FNTP Refurbishment Works 6th July 2005
FNTP New B Extension 30th September 2005
Group 1 COD (+450MW + 30MIGD) 1st May 2008
Project COD (2000MW 160 MIGD) 20th July 2008
 